Details of works planned for the Levenmouth area in 2023/24 are included below.
Key to progress indicators:
Works still to commence onsite | Planned |
---|---|
Works in progress | Started |
Construction works complete | Complete |
Construction works postponed | Postponed |
Road improvements planned for 2023/24
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
21 | Leven | Linnwood Drive | £154,000 | Complete |
21 | Leven | C1 Kennoway Road | £105,000 | Complete |
21 | Leven | Old Mill Court | £22,000 | Complete |
21 | Rural | U074 by Drumeldrie | £71,000 | Postponed |
21 | Rural | U084 (B927 to C59) | £66,500 | Complete |
22 | East Wemyss | McDuff Street (Alexander Street to Main Avenue) | £51,000 | Complete |
21 | Kennoway | A916 Sandy Brae (Old Station Road to New Road) | £159,000 | Complete |
22 | Rural | A915 (Three sections of Standing Stane Road) | £124,500 | Postponed |
Footway improvements planned for 2023/24
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
21 | Leven | Beech Park Phase 2 | £48,000 | Complete |
22 | East Wemyss | Approach Terrace | £61,500 | Complete |
21 | Leven | Anderson Street | £7,000 | Postponed |
21 | Kennoway | Castle Terrace Phase 2 | £63,000 | Complete |
21 | Leven | Hawthorn Street Phase 2 | £40,000 | Postponed |
22 | Methil | Sycamore Ave | £53,000 | Complete |
Lighting improvements planned for 2023/24
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
Windygates | Kennoway Road | £87,500 | Complete | |
Kennoway | Sandy Brae, New Road, Cupar Road | £119,000 | Complete | |
21 | Kennoway | Swards Place, Springbank & Viewforth Place | £84,000 | Complete |
22 | Methil | Methil Brae | £22,000 | Complete |
22 | Methil | Keir Hardie, Turner Cres, Barrier St, Sea Rd Cul-de-sac | £90,000 | Complete |
Traffic Management improvements planned for 2023/24
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
21 | Kennoway | A916 Sandybrae (speed reduction measures) | £20,000 | Complete |
21 | Kennoway | Springbank Road (Speed Reduction Measures) | £10,000 | Complete |
21 | Bonnybank | Cupar Road, A916 (Speed Reduction Measures) | £15,000 | Complete |
22 | Buckhaven | Sandwell Street (Speed Reduction Measures) | £10,000 | Complete |
22 | Methil | Kirkland Gardens (remove raised roundabout) | £34,000 | Planned |
Structural Services planned for 2023/24
Ward | Town | Location | Progress |
---|---|---|---|
Planned patching programme for 2023/24
Ward | Town | Location (Click for map) | Budget | Progress |
---|---|---|---|---|
21 | Windygates | U041 Milton Road | Planned |
Cycleways programme for 2023/24
Ward | Town | Location (Click for map) | Budget | Progress |
---|