Ramsay Court Demolition

Ramsay Court

Property Services provided contract administration services for this project.

This was the final phase of high rise demolition in Kincardine, with two adjacent blocks of flats being demolished in 2010. The initial phase provided space for the construction of new low rise social housing, with Ramsay Court providing decant accommodation for the remaining tenants in the area, while the new housing was constructed. The demolition was carried out using explosives and required extensive liaison with statutory authorities and neighbours, as well as very careful planning.

The demolition has made a significant difference to the urban environment in Kincardine, with improvements both visually and in quality of life.

Details

Location: Kincardine

Value: £311,000

Start Date: September 2012

End Date: May 2013

Main Contractor: Dem-Master Demolition Ltd