North East Fife Area Roads Programme 2025-26

Map of North East Fife area

Details of works planned for the North East Fife area in 2025/26 are included below.

Key to progress indicators:

Works still to commence on-site Planned
Works in progress Started
Construction works complete Complete
Construction works postponed Postponed

Carriageway surfacing planned for 2025/26

WardTown Location (Click for map)BudgetProgress
17 Rural A919 £105,000 Postponed
17 Guardbridge A919 Main Street £387,000 Postponed
20 Cupar A913 Balgarvie Road £195,000 Complete
16 Falkland West Port £35,000 Complete
16 Rural C23 at Drummy Wood £594,000 Planned
17 Tayport Nelson Street/Shanwell Road £360,500 Complete
17 Balmullo Lucklawhill £182,500 Complete
20CuparA91 West Port to Bonnygate£87,000Complete
16 Newburgh Mugdrum Place £22,500 Complete
16 Newburgh Anderson Street £60,500 Complete
16 Newburgh Livingstone Street £62,000 Complete
18 St Andrews Craigtoun Road £141,000 Complete
20 Cupar Burnside North, Bank Street and Upper Dalgairn £119,000 Complete
16 Rural U095 (Near Gateside) £237,000 Complete
17 Balmullo Hayston Park £70,000 Complete
16 Rural B937 £104,000 Postponed
19 Rural U067 (Near Carnbee) £112,000 Complete
19 Rural U066 £62,500 Complete
17 Tayport King Street/Provost Road £51,000 Complete
19 Colinsburgh B942 Main Street £188,500 Complete
19 Anstruther Burnside Place £105,00 Postponed
19 Anstruther Burnside Terrace/B9131 Caddies Burn £60,500 Postponed
17 Rural U063 £77,500 Complete
19CarnbeeU065£81,000Complete
17 Rural B945 - U045 to A914 St Michaels £602,000 Postponed
20CeresMain Street£74,000Complete
16AuchtermuchtyA91 Low Road£254,000Started
16RuralA914 Kettlebridge to Pitscottie£579,000Complete
16NewburghMonkswell Road
£39,000Complete

Footway surfacing planned for 2025/26

WardTown Location (Click for map)BudgetProgress
17 Leuchars Main Street £51,500 Postponed
16 Kettlebridge A914 Cupar Road £39,000 Complete
18 St Andrews Cairnsden Gardens £60,000 Complete
16 Rural A913 Cupar Road £16,500 Planned
18 St Andrews James Street £7,500 Postponed
20 Cupar Westfield Road £40,000 Complete
18 St Andrews Lade Braes Walk £21,000 Postponed
20 Cupar Braehead Phase 1 £31,500 Complete
18St Andrews
Scooniehill Road Phase 1
£48,000Complete

Street lighting column replacements planned for 2025/26

WardTown Location (Click for map)BudgetProgress
17 Leuchars Main Street £164,500 Complete
19 Cellardyke Lady Walk, Mayview Avenue, March Crescent, Shore Street Cellardyke £242,500 Complete
19 Crail Marketgate & Balcomie Road £67,000 Postponed
16 Kettlebridge Cupar Road £54,000 Complete
16
LadybankCommercial Road
£40,000Complete
18St Andrews
Scooniehill Road Ph1
£120,000Complete
19 Pittemweem Ninian Fields £39,000 Complete
18 St Andrews Canongate £87,000 Planned
18 St Andrews Bogward Road £81,000 Planned
18 St Andrews Winram Place, Crawford Gardens, Balrymonth Courth £84,000 Planned
18 St Andrews North Castle Street / East Scores / The Scores £150,000 Complete
18St AndrewsMoir Cres, Leonard Gardens,Armit Pl, Doocot Road, Lawhill Gardens, Morton Cres, Carron Place, path 491/158, Windsor Gdns, Reid Gdns, Aikman Pl£225,000Complete
19St AndrewsSt Andrews Road & access at Waid Academy£15,000Complete

Road safety and traffic management improvements planned for 2025/26

WardTown Location (Click for map)BudgetProgress
20 Springfield C31 £10,000 Planned
16 Newburgh Abernethy Road £10,000 Planned
19 Elie The Toft / The Granary £20,000 Planned
19 Elie High Street £20,000 Planned
20 Ceres St Andrews Road £15,000 Started
18 St Andrews Strathkinness Low Road £10,000 Planned
17 Newport Tay Street £10,000 Planned
19 A915 North of Higham Toll £25,000 Planned
20 Pitlessie A914 £5,000 Planned
20 Pitscottie B939 £8,000 Planned
17 Newport West Road & Naughton Road £20,000 Planned

Surface dressing and treatments programme planned for 2025/26

WardTown Location (Click for map)Budget Progress
    

Road marking refurbishment programme for 2025/26

WardTown Location (Click for map)Budget Progress
20CuparA91 Bonnygate Complete
20CuparA91 Carslogie Road to Westport Complete
20CuparA91 St Catherine Street Complete
20CuparA914 South Road Pt1 Complete
20CuparA914 South Road Complete
20CuparB940 Pitscottie Road Complete
20CuparBank Street Complete
20CuparBlalowan Park Complete
20CuparCrossgate Complete
20CuparHill Crescent Complete
20CuparMillgate Complete
20CuparMoathill Road Complete
20CuparNorth Union Street Complete
20CuparSkinners Steps Complete
20CuparSouth Bridge Complete
17LeucharsA919 Main Street Complete
17LeucharsA919 Station Road Complete
17LeucharsA919 Main Street Pt2 Complete
17TayportB945 St Michael’s to Tayport Complete
17RuralB945 St Michaels to Tayport Rural Complete
17RuralB945 Tayport Rural to Tayport Gateway Complete
17TayportB945 Tayport gateway to Scotscraig Drive Complete
17Newport On TayB946 Tay Street Complete
17Newport On TayB995 Cupar Road Complete
17Newport On TayB946 Riverside Road Complete
17Newport On TayB946 St Fort Road to Castle Brae Complete
17Newport On TayWest Road Complete
17Newport On TayB946 Naughton Road Complete
17WormitB946 Wormit to A92 junction Complete
17LeucharsMain Street Complete
17Newport On TayB946 High Street Complete
18St AndrewsA915 Bridge Street Planned
18RuralA915 St Andrews rural Planned
18St AndrewsA917 Abbey Walk Planned
18St AndrewsA917 South Street Planned
18St AndrewsB939 Hepburn Gardens Planned
18St AndrewsB939 Strathkinnes Low Road Planned
18St AndrewsBell Street Planned
18St AndrewsBogward Road Planned
18St AndrewsCannongate Planned
18St AndrewsForest Place Planned
18St AndrewsHepburn Gardens Planned
18St AndrewsLargo Road Planned
18St AndrewsMelville Road Planned
18St AndrewsStrathkinnes High Road Planned
18St AndrewsCraigtoun Road Planned
18St AndrewsThe Scores Planned

Active Travel programme for 2025/26

WardTown Location (Click for map)BudgetProgress
  Newport-on-Tay Birkhill Avenue to Newport PS (2022 Newport to Wormit new path) £50,000 Planned
 LeucharsStation Road£240,000Planned

Bridges and structures programme for 2025/26

WardTown Location (Click for map)Budget Progress
    

Our use of cookies

Some cookies used are essential to providing a service, while others help us improve your experience and provide us with insights into how the site is being used.

For more detailed information about the cookies we use, see our Cookies page.

Cookie preferences