North East Fife

Details of works planned for the North East Fife area in 2024/25 are included below.

Key to progress indicators:

Works still to commence onsite Planned
Works in progress Started
Construction works complete Complete
Construction works postponed Postponed

Road improvements planned for 2024/25

WardTown Location (Click for map)Budget Progress
17GuardbridgeA919 A91 Roundabout to Inner Bridge£387,000Postponed
17RuralA919 Guardbridge Inner Bridge to Toll Road, Leuchars£105,000Postponed
20CuparA913 Balgarvie Road£197,500Postponed
19RuralB940 (A915 Junction to B9131 Junction)£985,500Complete
19RuralB940 (B9171 to B9131)£757,000Complete
16LadybankB9129 Commerical Crescent£126,500Planned
19ArncroachC61 Main Road£88,000Complete
17RuralU042 (B945 to A92T)£51,500Complete
19RuralB9131 (From B940 to North of U057, before Beley Bridge)£116,000Complete
17RuralB945 - U045 to A914 St Michaels£602,500Planned
19RuralB942 Colinsburgh - B9171 west to Easter Pitcorthie£202,000Planned
16RuralA912 - New Inn to Falkland£321,000Planned
16RuralU089 - A92 to A913£149,000Planned
16AuchtermuchtyU094 Mournipea - B936 west for 500 metres£74,500Planned
16LadybankB9129 Melville Road£95,000Planned
16RuralU113 - East Lomond Car Park to A912£222,000Planned
20CuparPrestonhall Industrial Estate£147,000Planned
17NewportSt Mary's Lane£9,500Planned
 RuralU023 (ward boundary to Falkland)TBAComplete

Footway improvements planned for 2024/25

WardTown Location (Click for map)Budget Progress
18St AndrewsQueens Gardens Ph 1 (west side)£100,000Complete
20CuparLady Wynd£35,000Planned
19PittenweemA917 Viewforth Place£52,500Planned
19PittenweemA917 James Street£52,500Planned
18St AndrewsScooniehll Road Phase 1 - Lamberton Place to Largo Road both sides (including short section on Largo Road to the Sub Station)£45,000Planned
18St AndrewsKilrymont Road Ph2 - Lamond Drive to Kilrymont Place (East Side)£70,500Planned
16RuralA913 Cupar Road - Opposite property 'Craigmill View' heading east to extent of new footway surface£55,500Planned
18St AndrewsHepburn Gardens - Electricity Sub Station to Signal Crossing£10,500Planned
19ElieStenton Row and The Toft -A917 to Property No 1 both sides including section to the south of The Terrace £50,500Planned
18RuralA91 - The Lodge Edenside to end of Adoption£104,500Planned

Lighting improvements planned for 2024/25

WardTown Location (Click for map)Budget Progress
18St AndrewsNorth Castle Street / East Scores / The Scores£122,500Planned
19PittenweemPittenweem Harbour£56,000Planned
19AnstrutherAnstruther Harbour and Shore Street£73,500Planned
18St AndrewsQueens Gardens£2,000Complete
20CuparLorraine Drive & Scotstarvit View£60,000Planned
20CuparMillbank / Brighton Road£48,000Complete
20CuparSandylands Road area£87,000Planned
18St AndrewsJamie Anderson Place£72,000Started
18St AndrewsPhase 6 - North Castle, East Scores, The Scores£150,000Planned
17LeucharsMain Street - near army base£134,000Planned
17TayportLink Road North (Caravan Park)£21,000Planned
16LadybankCommercial Road£18,000Planned
18St AndrewsScooniehill Road Ph1£87,000Planned
19AnstrutherSt Andrews Road & access at Waid Academy£25,500Planned
19AnstrutherLady Walk, Mayview Ave, March Cres, Shore Street Cellardyke.£78,000Planned
18St AndrewsMoir Crescent, Leonard Gardens, Armit Place, Doocot Road, Lawhill Gardens, Morton Crescent, Carron Place, path 491/158, Windsor Gardens, Reid Gardens, Aikman Place£225,000Planned

Traffic Management improvements planned for 2024/25

WardTown Location (Click for map)Budget Progress
19 & 21RuralA917 Upper Largo to Crail£2,000Complete
15RuralA91 Melville Lodges to Strathmiglo£5,000Complete
17GuardbridgeMain Street (speed reduction measures)£15,000Postponed
16LethamThe Row (speed reduction measures)£10,000Postponed
20CraigrothieA916 & B939 (Traffic calming & junction improvements)£30,000Planned

Structural Services planned for 2024/25

WardTown Location (Click for map)Budget Progress
    

Planned patching programme for 2024/25

WardTown Location (Click for map)Budget Progress
    

Cycleways programme for 2024/25

WardTown Location (Click for map)Budget Progress